The foundation is being prepared at the construction site

The foundation is being prepared at the construction site 01.03.2020

The foundation is being prepared at the construction site

Work is actively underway on the Hydrocracking Complex being constructed at the Afipsky NPZ.

As of February 26th, 5,117 piles were installed at the Hydrocracking site (95% of the planned amount), and 460 piles (17%) were installed at the Hydrogen Production Unit site. It is planned that in March pile driving works will be completed at the aforementioned site. 548 cubic meters of foundation were implemented at the Hydrocracking site (1 % of the total project volume).

– All works on the two facilities are being carried out in accordance with the schedule, - commented Igor Sosnovets, head of the Hydrocracking Complex Construction Department. – The total number of workers of the General Contractor Promfinstroy JSC is 357 people, equipment - 62 units. In the future, based on preparation of detailed design documentation for the project and the facility completion, it is planned to engage more labor resources, as well as vehicles and machinery.
Soon, the manufacturing plants will start producing 700 tons of steel structures and this is only the first batch of the "Hydrocracking Unit" complex.
Igor Sosnovets added that the foundations are scheduled to be completed in March-April. This work will be carried out at the sites of the Hydrocracking and Hydrogen Production Units.
In addition, foundation work will be carried out for oversized equipment as well as preparation of platforms for lifting machines involved in the installation of oversized equipment.