General contractor increases its presence

General contractor increases its presence 30.01.2020

General contractor increases its presence

The pace of work is gaining ground at the site of the Hydrocracking complex. As of January 27, 4145 piles were installed (33% of the planned amount). Piling works are in progress. 0.018 % of monolithic foundations are ready against the design’s target (total-70,293 square meters).
- The General Contractor JSC «Promfinstroy» is increasing its presence on the site – says Igor Sosnovets, Head of the Hydrocracking Complex Construction Department. Currently, 236 specialists are working here and 45 units of equipment are in operation. The pace of work is in line with the construction deadlines.
A significant amount of work is planned for February. Earthwork will be carried out for all units, namely: vacuum gas oil hydrocracking unit, hydrogen production unit and sulfur recovery unit. It is expected that piling works of the Hydrocracking complex will be completed during this month. At the other two sites, the piling works will continue. According to Igor Sosnovets, at the end of the month, deliveries of crane facilities for the installation of oversized equipment will commence at the Afipsky Refinery.
In addition, in February, the manufacturing of steel structures will start at the contractor plants. Installation of above structures is scheduled to start at the construction site in April.